Southwark Bridge Inspection

Bell Access supplied a team of four IRATA qualified technicians to undertake a visual & photographic survey to the underside of Southwark Bridge.

The team allowed for one span to be inspected per day causing minimal disruption to the river traffic and Port of London Authority.

Water safety support was in attendance throughout the project to aid with rescue in the event of an incident at height and assist with river access and equipment Logistics.

Utilizing rope access and fall arrest technics the team where able to access all areas of the underside of the structure.

London-Southwark-Bridge-2

Project Details

Framework: City of London
Client: AECOM
Duration: 1 Week

Get In Touch

We understand your needs may not have been covered by any of the above, but we enjoy a challenge, so if you require something different why not get in touch and we can discuss how we can help.

cropped-IMG_2961.jpg
Bell-Access-Engineering-Header-Logo

Join The Team