Bell Access & Engineering Ltd worked closely with STORY Contracting & Network Rail to provide a solution for a challenging work site. The aim was to minimise disruption while gaining access across the viaduct, the environmental challenges included operating in a steep sided gorge, crossing rivers & public access foot paths and keeping noise to a minimum while working close to local housing.
To minimise disrupting rail traffic and to ease access throughout the structure a cable system was installed to allow cradle access to all piers, span walls and arch barrels. The initial program involved working in the hours of darkness to diamond core 220no. 32x2000mm vertical cores to stabilise the structures parapet wall.
Further drilling on this project included:
Framework: Network Rail
Client: STORY Contracting
Duration: 27 weeks